The reconstruction of Tissima Stadium in Casablanca is moving forward with the launch of an international open tender for the fifth construction package, covering high- and low-voltage electrical systems and facade lighting.
The project is overseen by the Royal Moroccan Football Federation (FRMF), acting as the project owner, and the National Agency for Public Equipment (ANEP), serving as the delegated project owner. Its estimated cost exceeds MAD 531 million, including taxes.
Under international tender No. 48/INF/2026/ST, the provisional bid bond has been set at MAD 7 million. The contract specifications provide for a 10-month completion period for the electrical works.
The project is being carried out under the architectural supervision of My Group Architect and the technical consultancy of a consortium comprising Grid and Diagonal Management.
The electrical package is designed to provide a reliable power infrastructure capable of supporting the stadium’s operations under different conditions. It includes the installation of a power delivery center and two electrical substations equipped with transformers rated at 1,600 kVA each, as well as four soundproof backup generators, each with a capacity of 1,500 kVA.
The system will also include uninterruptible power supplies to protect sensitive equipment against sudden outages, alongside dedicated power networks for lighting the facade, roof and stands. Other installations will supply perimeter screens, illuminated VIP-box features and the phototherapy systems used to support the stadium’s natural grass.
Beyond power infrastructure, the works will cover low-voltage and communications technologies required for major football events. These include an integrated television broadcasting network, sound systems for the stadium and conference rooms, internet-based television broadcasting and wireless internet coverage designed to reach 99.95% of the venue.
Security and public safety systems will include advanced fire detection and crowd evacuation systems meeting Category 1 requirements, supported by a video surveillance network and access-control systems.
The contract specifications also require the use of building information modeling (BIM) in accordance with standards and regulations adopted by FIFA, alongside a quality assurance plan covering all stages of implementation.
To qualify for the tender, competing Moroccan companies must hold first-category classification in electrical works, low-voltage systems and audiovisual equipment.
The project also includes provisions intended to support the domestic economy. The successful contractor will be required to prioritize products and materials manufactured in Morocco, provided they meet the required technical specifications. The contract further stipulates that local workers and skilled labor must account for up to 20% of the workforce.
Located on a 6.62-hectare site in the Ben M’Sik-Sidi Othmane district of Casablanca, the stadium is being rebuilt following the complete demolition of its former structure, which had deteriorated and no longer met contemporary requirements.
The new venue is planned as a modern, multipurpose stadium with partial roofing and a seating capacity of 30,000.