Morocco mobilized up to 38% of its available electricity production capacity to assist Spain, which suffered a widespread power outage affecting much of its grid. In response to an emergency request from Red Eléctrica Española (REE), Morocco’s national electricity utility, ONEE, activated the two existing interconnection lines that run beneath the Strait of Gibraltar.
“We re-established the interconnections, automatically disconnected due to the sudden collapse of the Iberian network, and made available a certain amount of energy to help restart power plants in southern Spain a spokesperson for REE told Spanish media.
The interconnection infrastructure linking Morocco and Spain consists of a dual-line system with seven submarine cables, stretching between the coastal substation of Fardioua, located 28 kilometers east of Tangier, and the Tarifa substation in the Cádiz province of southern Spain. This system has an operational capacity of 1,400 megawatts.
Immediately after the outage, Morocco,which had previously been importing 778 megawatts, redirected 519 megawatts to Spain.
Morocco’s domestic grid remained virtually unaffected thanks to a swift deployment of coal and natural gas combined-cycle power plants helped bridge the gap left by the Spanish blackout.
The current interconnection, first constructed in 1988, is expected to be reinforced with two additional lines starting in 2028, further strengthening energy collaboration across the Mediterranean.