Sound Energy said the Tendrara gas project in eastern Morocco has crossed a key industrial threshold after successfully flowing its two development wells and completing commissioning of core surface infrastructure, marking the project’s transition toward phased production.
The UK-based operator said wells TE-6 and TE-7 were brought into flow during start-up operations, allowing full testing of the gas gathering system, including wellheads, pipelines, control valves, heat exchangers, liquid separators and flaring facilities.
The two wells, located about two kilometres apart, were used to validate different sections of the network under operating conditions.
The company said the successful commissioning confirms the technical readiness of Phase I and clears a prerequisite for commercial first gas.
On the power side, the Tendrara site is now equipped with nine electricity generators, seven gas-fired and two diesel, designed to ensure continuous supply in harsh conditions. Gas-powered units are expected to switch to locally produced gas in coming weeks, replacing diesel and lowering operating costs and direct emissions.
Sound Energy also said Moroccan authorities approved an extension of the Anoual exploration permits until September 2028, alongside a reduced licence area and a firm commitment to drill a Triassic-targeted exploration well.
While short-term financing remains under review, the company said recent progress shifts the project firmly into the execution phase.